After many months and lots of background work, we are extremely happy to announce that the construction work for the Padel courts will recommence on Monday the 3rd of March 2025.
Estimated timings (weather permitting)
28th February - Contractors will be onsite to commence site set up.
3rd/4th March - Canopy will be delivered, and build will commence, build will take up to 3 weeks.
Court installation will follow - 2 weeks
Construction of the second entrance, additional parking, disability ramp and mini tennis court a further 8 weeks.
We are expecting very little, if any disruption to the day-to-day operation of the club, we will keep you posted.
Based on the times above we are targeting an opening date in late May/early June.